3 week look ahead 3/18
Look Ahead
45 Bartlett Crescent, Brookline
Week 03/18
· Forming footings and walls in preparation for concrete pours.
· Rebar delivery expected 3/21
Week 03/25
· Forming footings and walls in preparation for concrete pours
· We are hopeful the first conrete pour for footings will be 3/27
Week 04/01
· Continuing to pour concrete