3 week look ahead 3/18

Look Ahead

45 Bartlett Crescent, Brookline 

Week 03/18

·     Forming footings and walls in preparation for concrete pours.

·     Rebar delivery expected 3/21

Week 03/25

·     Forming footings and walls in preparation for concrete pours

·  We are hopeful the first conrete pour for footings will be 3/27

Week 04/01

·     Continuing to pour concrete