3 week look ahead 3/25

Look Ahead

45 Bartlett Crescent, Brookline 

Week 03/25

·     Continued footing prep

·     Forming and pouring footings

·     Elevator pit pouring, rebar deliveries and installation

·     Forming walls at the back of the property

Week 04/01

·     Concrete pours

Week 04/08

·     Concrete pours