3 week look ahead 3/25
Look Ahead
45 Bartlett Crescent, Brookline
Week 03/25
· Continued footing prep
· Forming and pouring footings
· Elevator pit pouring, rebar deliveries and installation
· Forming walls at the back of the property
Week 04/01
· Concrete pours
Week 04/08
· Concrete pours