3 week look ahead 3/11
45 Bartlett Crescent, Brookline
Week 03/11
· Shoring is complete
· Site work continues. Hauling dirt and digging footings
· Foundation excavation
Week 03/18
· Form footings
Week 03/25
· Pour concrete
EDIT PAGE
45 Bartlett Crescent, Brookline
Week 03/11
· Shoring is complete
· Site work continues. Hauling dirt and digging footings
· Foundation excavation
Week 03/18
· Form footings
Week 03/25
· Pour concrete