3 week look ahead 3/11

45 Bartlett Crescent, Brookline

 

Week 03/11

·     Shoring is complete

·     Site work continues. Hauling dirt and digging footings

·     Foundation excavation

Week 03/18

·     Form footings

Week 03/25

·     Pour concrete