3 week look ahead 9/30
9/30 - Wrapping up foundation
10/7 - Site backfilling/grading, underground site plumbing
10/14 - Stairwell CMU, Garage floor slab
9/30 - Wrapping up foundation
10/7 - Site backfilling/grading, underground site plumbing
10/14 - Stairwell CMU, Garage floor slab