3 week look ahead 10/28
Week of 10/28 - Backfilling, grading/stone, install temp power post, trench for underground, install oil/gas separator, interior perimeter drain
Plumbing to start underground plumbing install.
Week of 11/4 - Backfill underground plumbing/perimeter drain etc. prep for slab on grade.
Plumbing wrap underground and awaiting wmra inspection on oil/gas separator.
Slab prep/rebar mesh install etc.
Week of 11/11- Start pouring slab on grade
Retaining wall at driveway etc. to be prepped and installed