3 week look ahead 10/28

Week of 10/28 - Backfilling, grading/stone, install temp power post, trench for underground, install oil/gas separator, interior perimeter drain

Plumbing to start underground plumbing install.

Week of 11/4 - Backfill underground plumbing/perimeter drain etc. prep for slab on grade. 

Plumbing wrap underground and awaiting wmra inspection on oil/gas separator.

Slab prep/rebar mesh install etc.

Week of 11/11- Start pouring slab on grade

Retaining wall at driveway etc. to be prepped and installed

Previous
Previous

3 week look ahead 11/4

Next
Next

3 week look ahead 9/30