3 Week look ahead 4/08

Look Ahead

45 Bartlett Crescent, Brookline 

Week 04/08

·     Continue with forms and rebar

·     Waterproofing foundation/elevator

Week 04/15

·     Concrete pours

Week 04/22

·     Concrete pours