11/18 Three week look ahead
Week of 11/18:
Surveyor- final as built complete and sent to steel
Plumbing- underground plumbing inspection and sign off.
Site - Backfill underground plumbing and finish interior grading and prep for garage slab.
Pittol- Start installing mesh rebar and prep for garage slab.
Electrical - Temp site power install and inspection. Locate main power entrance into building for coring.
Delivery of retaining wall block.
Week of 11/25:
Site - retaining wall prep/trenching for block wall.
Start install of block retaining wall.
Concrete - Pour garage slab. Multiple pours
Week of 12/2:
Concrete - garage slab completion
Completion of block wall
Awaiting steel delivery