11/18 Three week look ahead

Week of 11/18:

Surveyor- final as built complete and sent to steel

Plumbing- underground plumbing inspection and sign off.

Site - Backfill underground plumbing and finish interior grading and prep for garage slab.

Pittol- Start installing mesh rebar and prep for garage slab.

Electrical - Temp site power install and inspection. Locate main power entrance into building for coring.

Delivery of retaining wall block.

 

Week of 11/25:

Site - retaining wall prep/trenching for block wall.

Start install of block retaining wall.

Concrete - Pour garage slab. Multiple  pours

 

Week of 12/2:

Concrete - garage slab completion

Completion of block wall

Awaiting steel delivery