11/11 3 week look ahead
Week of 11/11:
Surveyor - shoot final points and plates for finishing up as-built.
Site - Finish main water piping install ( 4’ domestic/6” fire), pressure test, backfill.
Plumbing- Finish underground plumbing, set floor drains/vents/etc.
Laborer- Seal and hydraulic cement oil/gas separator. Prep for MWRA inspection.
Electrical- Temp power post inspection prior to live power.
Week of 11/18:
Surveyor: final foundation as-built received and submitted to Ren’s Steel.
Plumbing: underground plumbing inspection and sign off.
Site: Backfill underground plumbing and finish interior grading and prep for garage slab.
Concrete - Start installing mesh rebar and prep for garage slab.
Electrical - Temp site power install and inspection. Locate main power entrance into building for coring.
Skyview- Delivery of retaining wall block.
Week of 11/25:
Site - retaining wall prep/trenching for block wall.
Skyview- Start install of block retaining wall.
Concrete - Pour garage slab. Multiple pours