12/2 Three week look ahead
Week of 12/2:
Plumbing - Underground plumbing inspection (passed, ready for backfill)
Week of 12/9:
Monday/Tuesday- MWRA Inspection
Steel - Drawing confirmation via Architect. Awaiting fabrication.
Site - Slab prep/grading
Week of 12/16:
Concrete - Slab mesh, form, pour slab
Steel - Awaiting steel.