12/2 Three week look ahead

Week of 12/2:

Plumbing - Underground plumbing inspection (passed, ready for backfill)

Week of 12/9:

Monday/Tuesday- MWRA Inspection 

Steel - Drawing confirmation via Architect. Awaiting fabrication.

Site - Slab prep/grading

 Week of 12/16:

Concrete - Slab mesh, form, pour slab

Steel - Awaiting steel.