3 week look ahead 2/26
45 Bartlett Crescent, Brookline
Week 02/26
· Lagging stopped until site is at grade.
· Demolition of last old foundation is complete.
· Site work continues in support, excavation for foundation and to finish lagging.
Week 03/04
· Continuing to haul dirt and bring site down to grade.
Week 03/11
· Diagonal bracing will be installed when at grade.