3 week look ahead 02/19

45 Bartlett Crescent, Brookline 

Week 02/19

·     Lagging stopped until site is at grade.

·     Demolition of last old foundation is complete.

·     Site work continues in support, excavation for foundation and to finish lagging.

Week 02/26

·     Continuing to haul dirt and bring site down to grade.

Week 03/04

·     Diagonal bracing will be installed when at grade.

Previous
Previous

3 week look ahead 2/26

Next
Next

3 week look ahead 02/05