3 week look ahead 8/5
8/5 - Site work continues. Digging footings.
8/12 - Rebar forming and excavation.
8/19 -Foundations and concrete to be scheduled.
8/5 - Site work continues. Digging footings.
8/12 - Rebar forming and excavation.
8/19 -Foundations and concrete to be scheduled.