3 week look ahead 6/3
6/3/24:
Site contractor installing exterior perimeter drain and backfilling of the done portion the foundation.
Waterproofing has finished waterproofing all completed foundation as well as the single sided form area.
6/10
DPW/sewer work scheduled to start Monday 6/10.
Pittol Concrete scheduled to be back on site Mon 6/10 to begin rebar and forming of single sided wall.
6/17
Site work continuing for steel delivery.