3 week look ahead 6/3

6/3/24:

Site contractor installing exterior perimeter drain and backfilling of the done portion the foundation.

Waterproofing has finished waterproofing all completed foundation as well as the single sided form area.

6/10

DPW/sewer work scheduled to start Monday 6/10.

Pittol Concrete scheduled to be back on site Mon 6/10 to begin rebar and forming of single sided wall.

6/17

Site work continuing for steel delivery.

Previous
Previous

3 week look ahead 6/10

Next
Next

3 Week Look Ahead 5/27