3 week look ahead 6/24

Still currently working on sewer in the street.

1 manhole installed and they are currently trenching 24” pipe up to next manhole.

Concrete team on site last Friday and Monday of this week tying rebar at single side wall. 

Next 3 weeks: finish street work, dig footings, rebar, forms, and concrete.