3 week look ahead 5/13
Week of 5/13
Elevator masonry
Site work
Sidewalk repairs
Pour concrete footings
Week of 5/20
Waterproofing footings
Back half of foundation to be poured
Week of 5/27
Form, tie rebar, and concrete pours
Start of DPW work
Week of 5/13
Elevator masonry
Site work
Sidewalk repairs
Pour concrete footings
Week of 5/20
Waterproofing footings
Back half of foundation to be poured
Week of 5/27
Form, tie rebar, and concrete pours
Start of DPW work