3 Week look ahead 4/22
Week of 4/22
Elevator masonry shaft to begin
Site work
Sidewalk repairs
Pour concrete footings
Week of 4/29
Waterproofing footings
Back half of foundation to be poured
Week of 5/6
Form, tie rebar, and concrete pours
Start of DPW work