3 week look ahead 01/29

45 Bartlett Crescent, Brookline

 

Week 01/29

·     Lagging being installed

·     Demolition of last old foundation

·     Site work continues in support, excavation for foundation

Week 02/05

·     Excavation continues, removing fill from site and bringing in new materials

Week 02/12

·     Ready for foundation