3 week look ahead 01/15

45 Bartlett Crescent, Brookline

 

Week 01/15

·     SOE work - 6 piles left to drill

·     Site work continues in support of SOE

Week 01/22

·     Site work and excavation

 Week 01/29

·     Site preparation

·     Ready for foundation – End of January